Van Phong 1 Thermal Power Plant: Completion of piling work for coal jetty
On 13th May, 2021, Pacific Corporation (Pacific) officially completed the piling work for coal jetty package of Van Phong 1 Thermal Power Plant. This is the result of determination and great efforts of the Board of Directors and employees of Pacific, especially the team of EPC Department, management and construction staff of Van Phong 1 Site Management Board to celebrate the 20th anniversary of the Corporation.

Representative of the Investor, Doosan General Contractor and Leaders of the Site Management Board of Pacific and Phu Xuan Consultation and Construction Joint Stock Company congratulated the completion of pile driving
Coal jetty is an open sea port type, which is located a distance 1.2km from the mainland, connected by a 1.2km access trestle supporting the road and conveyor system to transport coal into the plant, with a width of trestle is 12m. Coal jetty structure is a combination of precast concrete beam and slap with cast in-stu pipe cap, all these structures are supported on a steel pipe pile foundation.
.jpg)
Overall of coal jetty package
Overcoming difficulties in extreme construction conditions at open sea area, highly dependent on weather conditions, Pacific has completed total of 630 piles, including 259 piles of access trestle system and 371 piles of the main berth. This result shows the efforts of active supervision and quality assurance of Pacific during the project implementation.
.jpg)
Final piling construction
Mr. Jong Ho Choi - General Site Manager, Doosan Group also sent a letter to congratulate this event and highly appreciate the efforts of Pacific Corporation.
Photos from the construction site:
.jpg)
Construction of pile cage steel

Pile welding
.jpg)
Prefabricated installation
.jpg)
Installation of prefabricated components
.jpg)
Construction of steel beams
Photos: Tùng Lý